What a Will B Safe Inspection Report Looks Like
Most contractors have never seen an independent inspector's report before they book one. Here is what arrives in your inbox within 24 hours of every visit, and why each part is there.
The report, page by page
- 1
Who it is for and where. The name and address of the person the inspection was carried out for, the site, and the location of the scaffold on it, so the report cannot be mistaken for another scaffold on the same job.
- 2
A description that actually describes the scaffold. Type, lifts, length, loading class, sheeting or netting, access, ties. "The scaffold" is not a description, and a stranger reading this report should be able to picture it.
- 3
Date and time of the inspection. The seven-day clock runs from here.
- 4
Findings. Any matter that could give rise to a risk, stated plainly and located precisely: lift, elevation, bay.
- 5
Captioned photographs. Every photo says what it shows and where it is. A photo without a caption is decoration.
- 6
Action taken on the day. What was put right on site, if anything.
- 7
Further action required. What the scaffolding contractor needs to do, and by when.
- 8
The verdict. Safe to use, safe with the actions above, or not to be used until rectified. A report that does not say is not doing its job.
- 9
Defects carried forward. Anything open from a previous visit stays on the report until it is closed, so nothing gets quietly forgotten.
- 10
Name, position and qualifications of the inspector. Mine, every time. The person who stood on the scaffold signs the report.
The summary email
The report is the legal record. The email is what gets things fixed. Within the same 24 hours you get a short email listing the actions that matter, in priority order, so a site manager can act on it without opening the PDF. Clients tell me this is the part they value most.
See a real one
If you would like to see a full report before you book, email info@willbsafe.co.uk or message me on WhatsApp and I will send you a recent one with the client, site and address details removed. Everything else is exactly as the client received it.
Why it is laid out this way
Schedule 7 of the Work at Height Regulations 2005 sets the eight particulars a report must contain. Everything else on the list is there because of what happens after an incident, an audit or an insurer's enquiry: the report has to be understood by someone who was never on site, months after the event. Reports are kept on site until the work is complete and for three months afterwards.